Friday, August 17, 2007

Week 16 8/13 - 8/17/2007

Week 16 - Windows, exterior doors, roofing, and gutters were installed. HVAC, electrical, and plumber got started inside. The front door and roofing color Michele picked out looks really great. Looks Nice!


Mike

Thursday, August 9, 2007

Week 14 & 15

8/1 - 8/8 - Keep forgetting to take pictures. Took a bunch last night. Roof is sheeted, fascia boards on and are primed and painted ready for gutters. Lots of details going on inside. Concrete was poured in the garage and the front porch...looks really good. Front porch will cure for a week and then will be sealed and finished and look really great. Windows & exterior doors were delivered yesterday and will be installed this week. Roofing and gutters should start this week. Fireplace delivery is delayed, plumbing rough-in, HVAC rough-in, and electrical rough-in should all start this week, hopefully they will all get here soon and get going.




Mike