Thursday, September 27, 2007

Week 19 - 22 (9/1 - 9/30)

Week 19 - Stucco Lath, Rough Plumbing, HVAC, and Electrical, misc. framing punch list stuff. I ran all of the low voltage communications cabling and tv cabling this weekend.

Week 20 - Fireplace installed, Lath for Stucco completed. Inspections completed with a small list of corrections (20 or so).


Week 21 - Corrections made, Insulation completed. Drywall started. Michele hung insulation on all interior walls, and we rented a trencher and put in french drains and irrigation trenches.

Week 22 - Drywall (Sheetrock) complete, inspected, stucco scratch coat completed. Tape and texture will start.

Things are going well, Michele is doing a bunch of selection and ordering of kitchen cabinets, appliances, tile, etc. This weekend we should be completing our french drains and irrigation pipes.

MC








Thursday, September 6, 2007

Week 18 8/27 - 8/31

More of the same....moving slow.

Week 17 - 8/20 - 8/24

No pictures...Rough Plumbing, Electrical, and HVAC are started. Moving very slowly, now begins the hard part of getting people to show up and finish.

Some things have kind of gone out of order and caused some issiues. Roof and gutters are on, but plumbing and air did not have the roof vents/jacks in. Gutters were installed, but down spouts can not be installed until after stucco. Gutters in front are to long because the front porch was not complete. The list goes on. Frustrating.