No pictures...Rough Plumbing, Electrical, and HVAC are started. Moving very slowly, now begins the hard part of getting people to show up and finish.

Some things have kind of gone out of order and caused some issiues. Roof and gutters are on, but plumbing and air did not have the roof vents/jacks in. Gutters were installed, but down spouts can not be installed until after stucco. Gutters in front are to long because the front porch was not complete. The list goes on. Frustrating.